The end of month deadline is fast approaching for the TVFC pavilion project and the final product is coming together nicely. In the past week alone the external doors have been fitted, industrial quality vinyl flooring has been laid, roof drainage installed, the external decking has been completed, two roller shutters installed for the canteen and the shower installed for the referees room. Currently the access ramp is being constructed, leaving only the canteen fit out, final plumbing installations and final external shed fittings to be completed.
The club is delighted with the quality workmanship provided by the Johns Lyng building team and associated contractors. All have delivered their component of the project in a timely and professional manner. Once officially open, all at the club will gain a great deal of satisfaction and pride in the final product.